Recalculate a bottom up target for selected nodes and roll up values to higher-level nodes in the hierarchy.
Note
If auto recalculation is enabled on the target, recalculations are automatic when dependencies change. You can manually recalculate a target any time whether auto recalculation is enabled or disabled. Auto recalculation is disabled by default, you can enable auto recalculations in the target settings.
Manually recalculate and roll up a target
Find the bottom up target you want to recalculate.
Click the menu â‹® > Recalculate & Rollup.
.png?sv=2022-11-02&spr=https&st=2026-04-09T22%3A51%3A07Z&se=2026-04-09T23%3A02%3A07Z&sr=c&sp=r&sig=YeBVVdnS4eWvXlQUh7UY2kI0Yz8hDXTWKwaNEaoxNWE%3D)
From the left menu, select one or more nodes you want to include.
Complete the following sections, as needed:
Section
Description
Effective Date
Toggle on to schedule a date when the recalculations and roll up will take effect. From the dropdown, select a month.
Recalculate
Toggle on to include the selected nodes in the recalculation for the target.
Roll Up
Toggle on to roll up the selected nodes into the target.
Click Update Target.